Friday, 17 May 2013

Catch Up 3 - Walls are Coming Up

Once the new brickies were on site they worked pretty fast bringing the walls up. These pictures show where we were by 24th April


Living Room - Willy's constantly telling me that it's going to be sooooooo small!



Concrete Jungle




Nice Curve :)

Thursday, 16 May 2013

Catch Up 2 - Beam & Block Floor

This was a nice stage to reach - good to be able to stand and see the levels and to our delight the floor will be higher that we had imagined meaning great views from pretty much everywhere :)

Beams Delivered

Flooring Installed


Catch Up 1 - Photos

Am obviously very bad at this blog lark! Trouble is we have had lulls in the build for several reasons - weather - problems with details from structural engineer etc - and then I get fed up and don't want to write about it and by the time we're back on building I've almost forgotten that I'd decided to do this blog.
Right now I've been encouraged on by a very kind lady, Nadia, who has featured this blog on her website in a list of 'Top 5 Inspirational Build Blogs' http://www.kensyard.co.uk/blog/2013/top-5-inspirational-self-build-blogs/ . She has accurately described my blog as 'sporadic' but that is no excuse not to continue!

So.... the last images in March were after the all the ground works were completed. Next the walls were built to damp proof course level and a membrane laid and covered with sand (next door's cat found this to be a fine place to dump over the next few days until the floor was laid - there'll probably be fossilised cat faeces under the house in years to come)




Me in the dining room dog in the garden

Monday, 25 March 2013

Attenuation Tank Tedium

This for me is very very dull but I feel obliged to write about it briefly as it's been quite a big annoying issue for us;
During the design stage, planning and working with our code assessor no mention was ever made to us that we would need an attenuation tank to reduce the flow of rain water into the public sewers. It was not included in the plans, costed or quoted for but when our builder met with our code assessor it was brought up as being a mandatory requirement! Why it was never mentioned by our architect I don't think we'll ever know - during the design stage we had paid for a report to be done to calculate the rain water run off and apparently this tank is necessary for the one in one hundred year storm so that our house doesn't cause excessive strain on the the sewers.
The short of it is we now have to set a tank in the garden approx 4 metres long by 1metre deep. sounds simple but in fact it necessitates extra drains and quite serious digging, layers of various materials etc etc- yes I feel like going to sleep talking about it too!!!
We've been quoted £11k for this very dull thing - money I would have much preferred to spend elsewhere on something I can actually see and enjoy - as if we haven't sunk enough money in the ground already.

Due to the mammoth cost our builders are now trying to get quotes from specialist drainage companies to see if they can do it any cheaper - watch this space!!!!!

Catch Up

Last time I posted I think that we were having problems with the ring beam due to the layer of cellcore being missed out and highlighted by the NHBC inspector. After a bit of argy bargy about who hadn't read the drawings correctly the ground works team were forced to re-do the beam which was completed just before the end of November. As you can see in the photo, the rest of the ground is just a mud bath - when we come off site we're a couple of inches taller with all the clay that clings to your wellies!


Ring Beam

So on to site with the brick layers.... The picture below shows the beginnings of the walls as it was left just before Christmas and before the snows and bad weather came.

Site Before Christmas


We did much mooching about on the site in that strange time between Christmas & New Year and came to the conclusion that the the work done by the brick layers was not of a very good standard - we're not builders but even a lay man can see when there's gaps and messy cement left all over the walls. We kept passing the site and nothing had moved on, We were patient as the weather was freezing but eventually called the builder to ask what's going on....... he'd sacked the brick layers as he wasn't happy with their work or attitude!!

We were okay with him getting rid of bad brickies but anxious to get things moving. By mid February a new lot were on site and woking well. The decision had been made to remove the original brick work and start anew and also to leave the garage to later as access will be tight to the back of the house once the garage is up.

Here are some photos of our lovely new walls going up to damp proof course level 





Looking up towards living room and next level up of hallway & utility


Retaining wall at back of the kitchen and under the utility room

looking down site towards the North





Section of curved wall

Monday, 31 December 2012

The Start of an exciting New Year Ahead


I can't say that I'll be sorry to say goodbye to 2012 with all the stresses of planning the build from the initial work with the architect through planning permission to choosing a builder and raising the funds (though some of it's been fun) but I'm very excited about the New Year to come!!

As you can see from the photo we have the small beginnings of the walls so we can only go upwards from here.... We'll be in our new home for 2013!! WHOHOO!!

Thursday, 20 December 2012

Ring Beam

After the piling the ring beam is built which joins all the piles together and forms a strong base on which to start building.

Lots of rainy weather but Graham and his gang of youths got on with it, digging, lining with the yellow stuff and inserting the rebar ready for the concrete to be poured. It all looked so lovely .........but then the NHBC inspector arrived on site and he said NO STOP!!!



He wanted the foundation dug 50ml deeper, a layer of sand put on the bottom and then a layer of cellcore (as you can see in my cool picture below) to allow for heave before the yellow stuff etc is laid.


So a great upheaval ensued. So annoying, but we obviously have to keep all these people happy. Even though building control and our structural engineer were satisfied with it as it was we won't get our NHBC certificate or our mortgage unless we conform to all the NHBC demands.

Next time we were on site it looked like vandals had been rampaging........

How depressing was that!!